17. Design and Construction of PAKTIKA SOROBI TO MOROW KOT Afghanistan
Project Name and Location
Design/Construction of 19.5 KM Asphalt Road Sarobi to Marow Kot, Paktika province, Afg hanistan
Contract #: W917PM-C-09-0074
Nature of Firm’s responsibility
Design & Construction
Completion date
25-May-11
Construction cost (including design)
US$- 15,092,305.24
Duration of design
70 Days
Duration of Construction
380 days
Project Owner
Ahdaas Construction Co / USACE
Project Scope:
The project is consistent of 19.5 KM Asphalt Road AHDAAS is as Prime Contractor with AED, and MIACC is working as subcontractor for Ahdaas Construction Co.