| 7. Design and Construction of NMH Annex, Phase I Utility Upgrades, (ANA) |
Project Name and Location |
Design and Construction of NMH Annex, Phase I Utility Upgrades, (ANA) at Pul-e-Mohamood Khan, Kabul, Afghanistan
Contract#: W5J9JE-13-C-0010. |
Nature of Firm’s responsibility |
Design and Construction, MIACC was the prime contractor |
Completion date |
15/May/2015 |
 |
Construction cost (including design) |
$660,900.00 |
Duration of design and Survey |
60 days |
Duration of Construction |
180 days |
Project Owner |
US Army Corps of Engineers / AED |
Project Scope: |
The project work was consisting of the Design and construction of underground electrical wiring, installation of 1000 Kv power transformer, installation of panel boards, construction of manholes/hand holes and construction of 20 meters elevated water tanks |

|
|