| 8. Design and Construction of ANA, Pol-e-Khomri Generator and Alternate Replacement |
Project Name and Location |
Design and Construction of Afghanistan National Army (ANA), Pol-e-Khomri Generator and Alternate Replacement, Baghlan, Afghanistan
Contract#: W5J9JE-13-C-0017 |
Nature of Firm’s responsibility |
Design and Construction, MIACC was the prime contractor |
Completion date |
30/Oct/2014 |
 |
Construction cost (including design) |
$570,200.00 |
Duration of design and Survey |
150 days |
Duration of Construction |
340 days |
Project Owner |
US Army Corps of Engineers / AED |
Project Scope: |
The project scope the replacement of the existing 3 generators each one 1 MW. The project included, but was not limited to: Survey, Design, Supply and installation of generator power plants consisting of 3 generators, each one 1 MW and its related components such as standby system, grounding, and installation of fuel tanks. |

|
|