Project Name and Location |
Design and Construction of ANA Camp Scorpion Electrical Upgrades at Kabul, Afghanistan
Contract#: W5J9JE-13-C-0020 |
Nature of Firm’s responsibility |
Design and Construction, MIACC was the prime contractor |
Completion date |
01/June/2014 |
 |
Construction cost (including design) |
$3,058,000.00 |
Duration of design and Survey |
120 days |
Duration of Construction |
250 days |
Project Owner |
US Army Corps of Engineers / AED |
Project Scope: |
The project work was consist of replacing and upgrading of the existing underground electrical medium and low voltage cables, construction of new trenches, manholes/hand holes and installation of 25 new medium voltage power transformers as well as MDBs/panel boards. |